The Maryland Legislature passed several bills affecting residential construction.
Friday, May 9, 2008
Legislative Update for Residential Construction
Wednesday, April 16, 2008
Maryland Legistlature Caps Retainage
This new law will not prohibit withholding of any amount due from the owner to the contractor, contractor to subcontractor, or subcontractor to lower-tiered subcontractor if the non-paying party reasonably determines that the contractor or subcontractor’s performance under the contract provides reasonable grounds for withholding the additional amount. Upon approval by the Governor, this new law will take effect on October 1, 2008.
Monday, April 14, 2008
Incorporation of the Prime Contract: A Hidden Benefit
Virtually every subcontract agreement incorporates by reference the prime contract between the general contractor and the owner. Too often subcontractors do not obtain a copy of the prime contract and consequently become bound to terms and conditions they have not seen much less read. Moreover, the contractual provision incorporating the prime contract may state that if a conflict exists the contract language must be interpreted in a way that favors the general contractor. For example it may state:
"In the event of variations, conflicts, or inconsistencies between or among the terms, provisions or conditions of this Subcontract and any other Contract Documents, the terms, provisions and conditions which grant greater rights or remedies to Contractor or impose higher standards with regard to the obligations, responsibilities and scope of work of the Subcontractor shall control."
This provision, while seemingly favorable to the general contractor, does provide a benefit to a subcontractor because it fails to address the "rights" of a subcontractor. Consequently, if the subcontract allows for a larger overhead and profit markup than the prime contract, the allowable overhead and profit markup is a "right" of the subcontractor, not an obligation, responsibility or part of the scope of the work; nor is a right or remedy of the Contractor. Thus, the stated overhead and profit of the subcontract will control.
These "precedence clauses" as they are called must be carefully drafted and reviewed. Moreover, as always, a subcontractor should obtain copies of all contract documents incorporated into the subcontract.
Sunday, April 6, 2008
Contractual Indemnity Provisions
The Maryland Court of Appeals recently reiterated the various legal principles that trigger indemnification rights. In the context of contractual indemnity provisions, the Court recognized three basic types of indemnity provisions: (1) indemnity against loss or damage, under which the indemnitee may not recover until it has made payment or otherwise suffered an actual loss or damage within the scope of the indemnity; (2) indemnity against liability, under which an action may be brought as soon as the liability is legally imposed, as when judgment is entered, even though no actual loss has yet been sustained (the judgment has not been paid); or (3) a promise by the indemnitor “to perform a certain act or make specified payments for the benefit of the indemnitee,” under which an immediate right
of action accrues upon the failure of the indemnitor to perform, regardless of whether any actual damage has been sustained.
As evidenced by these three types of contractual provisions, the risk and exposure for the party providing indemnification in a contact can vary greatly depending upon the type of indemnification provision. Consequently, the indemnification provisions in construction contracts warrant careful scrutiny before execution.
Friday, March 21, 2008
Getting Paid: Maryland's Prompt Payment Act
The Maryland Prompt Payment Act requires timely payment to contractors performing work and furnishing materials, even in situations where the contract does not specify the payment schedule. The timing of payment depends on whether the work performed by the contractor was for an owner or for another contractor. If the contract does not provide specific dates or times for payment, payment of any undisputed amount owed under the terms of the contract must be made within 30 days after the day on which the occupancy permit is granted or 30 days after the day on which the owner or the owner’s agent takes possession, whichever is earlier. If the contract provides for specific dates or times for payment, the contractor must be paid any undisputed amount within 7 days after the date or time specified in the contract. In situations where the contract is not with an owner, but with another contractor, any undisputed amount owed to the subcontractor must be paid within 7 days after the contractor receives payment for the subcontractor’s work or materials. The Maryland Prompt Payment Act, however, does not apply to any contracts with public entities, including the State of Maryland, a county, a municipal corporation, a board of education, or a public authority or instrumentality. In addition to obtaining the undisputed payments, other remedies to contractors under the Maryland Prompt Payment Act include interest from the date the court determines that the amount owed was due and, in the event of a showing of bad faith by the non-paying party, attorney’s fees.
If you have any additional questions regarding the Maryland Prompt Payment Act, please contact Michael W. Siri at siri@bowie-jensen.com.
Wednesday, March 12, 2008
Application of Mechanic's Liens: Removable Machines
Wednesday, February 27, 2008
Bid Protests: Timing
In a recent Maryland State Board of Contract Appeals (“Board”) case, the Board found that a contractor failed to file a timely bid protest. The Board ruled that the bid protest should have been made when the construction company knew or should have known the basis for its protest and not at the time the bid was awarded. A high burden is placed on any contractor submitting bids for State contracts, because a bid protest may need to be filed before the bid is awarded or repercussions felt by the contractor.
In this most recent case, the State Highway Administration (“SHA”) accepted invitations for bids for a Community Safety and Enhancement project (“Contract”). The bid of the lowest bidder was announced as “irregular” because of insufficient bid security; however, subsequent to the opening of the bids, the SHA found that the low bidder’s bid was valid and effective. The low bidder was then awarded the Contract. After being informed by SHA of the award of the Contract, a bid protest was brought by the second lowest bidder. The Board ultimately found that the bid protest should have been brought within seven days from the time the lowest bidder’s bid was deemed “irregular” and not within seven days after the bid was awarded. The Board, as it has done numerous times in the past, places a strict interpretation on the timing of a bid protests as it relates to a construction company’s basis for the protest. As such, if you intend to bid any public projects in Maryland, be vigilant in determining whether all proper procedures have been followed. As soon as there is a violation, even if it occurs prior to the bid being awarded, a bid protest may be your only option to protect your rights.
If you have any further questions on bid protests or construction law, please contact Michael W. Siri at siri@bowie-jensen.com.
